Bruce Beach Drain

Share on Facebook Share on Twitter Share on Linkedin Email this link
Bruce Beach Drain Watershed map

In 2018 the Director of Public Works signed a petition for a Municipal Drain to alleviate flooding and provide improved drainage control on Bruce Beach Road North of the 8th Concession.

On November 19, 2018, Council appointed Dietrich Engineering to prepare the report which on May 3, 2021, the responsibility was transferred to Headway Engineering.

Dietrich Engineering Limited attended the October 14, 2020, Council Meeting to provide Council with an update on the project, and to discuss potential phasing options which will allow for the construction of the most critical components of the design as soon as possible to increase the safety of the public. A description of the possible phasing of the south portion of the project is as follows:

1) Phase I

Phase I includes the construction of the detention facility east of Lake Range Drive; the Lake Range Drive road crossing; and improvements to the ravine downstream of Lake Range Drive to Bruce Beach Road.

2) Phase II

Phase II includes the construction of a drainage system directly affecting properties on the east side of Bruce Beach Road between Concession 8 Road and the ravine, and an outlet to Lake Huron.

The north portion of the Bruce Beach Municipal Drain was removed from the original municipal drain project in November 2020 as the majority of the storm water generated in this area originates on the municipal road allowance and the proposed infiltration gallery to be constructed is within the municipal road allowance. Therefore, this section is similar to a municipal storm sewer project that generally involves providing road drainage by constructing a storm sewer or open ditch.

The Township had provided direction to the Engineer to apply for an Emergency Order (Section 124) for the Drainage Act to allow an accelerated construction of the storm water retention facility.

On October 1, 2021, the Township received confirmation of the approved drainage project as defined in the engineer’s report for the Bruce Beach Road Municipal Drain – Phase 1 to be an emergency within the meaning of Section 124 of the Drainage Act. This designation allowed for the construction of Phase 1 of the Bruce Beach Municipal Drain (pond, ravine work) to proceed without risk of procedural violations under the Drainage Act.

On July 19, 2021, Council accepted the Bruce Beach Municipal Drain Phase 1 report prepared by Headway Engineering and granted provisional approval.

Three appeals to the assessment were received by the Township, a hearing will be held in March 2022.

Preliminary work on Phase II of Bruce Beach Drain has commenced with more information to follow in 2022.


In 2018 the Director of Public Works signed a petition for a Municipal Drain to alleviate flooding and provide improved drainage control on Bruce Beach Road North of the 8th Concession.

On November 19, 2018, Council appointed Dietrich Engineering to prepare the report which on May 3, 2021, the responsibility was transferred to Headway Engineering.

Dietrich Engineering Limited attended the October 14, 2020, Council Meeting to provide Council with an update on the project, and to discuss potential phasing options which will allow for the construction of the most critical components of the design as soon as possible to increase the safety of the public. A description of the possible phasing of the south portion of the project is as follows:

1) Phase I

Phase I includes the construction of the detention facility east of Lake Range Drive; the Lake Range Drive road crossing; and improvements to the ravine downstream of Lake Range Drive to Bruce Beach Road.

2) Phase II

Phase II includes the construction of a drainage system directly affecting properties on the east side of Bruce Beach Road between Concession 8 Road and the ravine, and an outlet to Lake Huron.

The north portion of the Bruce Beach Municipal Drain was removed from the original municipal drain project in November 2020 as the majority of the storm water generated in this area originates on the municipal road allowance and the proposed infiltration gallery to be constructed is within the municipal road allowance. Therefore, this section is similar to a municipal storm sewer project that generally involves providing road drainage by constructing a storm sewer or open ditch.

The Township had provided direction to the Engineer to apply for an Emergency Order (Section 124) for the Drainage Act to allow an accelerated construction of the storm water retention facility.

On October 1, 2021, the Township received confirmation of the approved drainage project as defined in the engineer’s report for the Bruce Beach Road Municipal Drain – Phase 1 to be an emergency within the meaning of Section 124 of the Drainage Act. This designation allowed for the construction of Phase 1 of the Bruce Beach Municipal Drain (pond, ravine work) to proceed without risk of procedural violations under the Drainage Act.

On July 19, 2021, Council accepted the Bruce Beach Municipal Drain Phase 1 report prepared by Headway Engineering and granted provisional approval.

Three appeals to the assessment were received by the Township, a hearing will be held in March 2022.

Preliminary work on Phase II of Bruce Beach Drain has commenced with more information to follow in 2022.


Tell your story

Help us identify the drainage issues on Bruce Beach Rd. by sharing stories and photos here. 

Thank you for providing your story. The story will be reviewed by staff and posted to the site within 2 business days. 

Please note: stories that are unrelated to the Bruce Beach Rd. Drainage project will not be posted on the site. While we appreciate your contribution and will take your comments into consideration, we want this project page to stay true to its purpose, the Bruce Beach Rd. drainage issues. 

CLOSED: This discussion has concluded.

  • Share on Facebook Share on Twitter Share on Linkedin Email this link

    Thoughts on the Concepts presented by DEL

    by pnewson, about 5 years ago

    This is a note from Peter, Huron-Kinloss taxpayer at Bruce Beach.  Based on a conversation with his son David (who will eventually be a Huron Kinloss taxpayer).  David is a professional engineer and has over 10 years’ experience in an urban drainage setting. 

    Good Morning:

    Below are my thoughts on the issue and the various alternatives proposed by the Township through DEL.

    Very little has changed physically on the beach (from the bottom of the hill to the Lake) in the last 20 years that would contribute to the increased occurrence and magnitude in flooding events on the beach, so... Continue reading

  • Share on Facebook Share on Twitter Share on Linkedin Email this link

    Misconceptions

    by Brian, about 5 years ago

    The flooding alone Bruce Beach Road south of Highland Dr. is a result of snow melt and rainfall during the annual Spring melt. It doesn't happen every year. It was bad last year, however due to gradual melting and little rain this Spring there has been no flooding. I am all in favour of alleviating this yearly cycle, but not by directing the water straight into the lake. The Township Road Allowance in this area is 40 feet wide. The road itself takes up about 20 feet. Therefore there is plenty of room for a ditch on each side of... Continue reading

Page last updated: 27 Jan 2023, 10:19 AM