Project Updates
June 22, 2026
Road preparation work by Kemptons and Public Work Staff will begin during the week of July 6, 2026. This will included removing asphalt, excavating any logs or stumps under surface of the road, and re-building the road surface. Work is expected to take approximately 2 weeks/street.
Affected residents have received notice. Any property within the road allowance ie. irrigation system, should be moved prior to construction.
April 20, 2026
Council accepted the bid from Lavis Contracting to pave Petum Crt and Tuscarora Rd.
January 2026
Council approved 2026 budget including re-paving of Petum Crt and Tuscarora Rd in Point Clark.
Questions & Answers
If you do not see the information you want above, please feel free to ask us a question. The project team will respond within 3 business days.