Point Clark Road Construction Projects 2025

At the April 23, 2025 Council approved several road construction projects to improve road conditions in Point Clark. This project has been awarded to Lavis Contracting. The scope of the work varies and some will only go forward depending on weather and contractor availability.

Planned:

  • Concession 4 Hill from lower Lake Range to Arthur St and 100m north on upper Lake Range. Surface pavement to be stripped, road graded, and re-paved. Projected timeline May-June.
  • Lurgan Lane. Surface pavement to be stripped, road graded, and re-paved. Projected timeline May-June.
  • Ash St., Spruce Cres, Cedar Close. Surface pavement to be stripped, road graded, and re-paved. Stormwater upgrades may also be included upon approval of tender. Projected timeline Late Summer - Fall 2025.

Tentative, pending weather and contractor availability:

Surface pavement to be stripped, road graded, and re-paved. Tentatively planned for the following roads during Late Summer - Fall 2025:

  • Winnebago Rd from Tyendinaga to Abenaki.
  • Tyendinaga Rd from Winnebago to Petum.
  • Tuscarora Rd from Lake Range Dr to Petum Ct.
  • Onandago Pl, Petum Crt. S

During these projects, the affected street will be restricted to local traffic only. The contractor will do their best to provide access to driveways as much as possible throughout the construction process. Road conditions will be monitored for dust control and treated as necessary to minimize dust but some airborne dust is inevitable. Restoration work will be completed after paving.

For more information or questions, contact the Township of Huron-Kinloss or continue to check here for updates.

Point Clark Road Construction Map

Project Updates

August 20, 2025

Kurtis Smith Excavating will begin construction on Cedar Close and Spruce Cr on September 8, 2025. Normal working hours will be from 7:00am - 6:00pm.

Bus companies have been notified. Garbage and recycling will be taken to curb at Concession 2 by the construction company when the road is closed to traffic.

July 31, 2025

Shouldering on Concession 4 Hill and Lurgan Lane was completed as of July 14, 2025.

Tender for Ash, Spruce, and Cedar Close storm sewers has been awarded to Kurtis Smith Excavating. Ash St will be re-paved. Spruce and Cedar Close will have new storm sewers and be re-paved. Work will start in September.

The Township expects that Winnebago and Tyendinaga will be re-paved this fall. Tuscarora and Onandago will be postponed to another year.

June 26

Tender closing for Ash, Spruce, Cedar Cl storm sewers on June 26 to be be approved by council.

June 23-27

Crews will return to do shouldering and lawn repair on Con 4 Hill and Lurgan Lane in the next 2 weeks.

June 2-13

Concession 4 Hill will be closed from June 2 - 13. Pavement to be stripped, graded, re-paved. Second coat to be applied Monday June 9, 2025. - Completed

Lurgan Lane to be stripped, graded, and re-paved. Paving to be done on Monday June 9, 2025. - Completed


Provide a short summary of your question.

You have 150 characters left

Provide detailed information relating to your question.

You have 500 characters left

Select a respondent from the list that you would most like to answer your question.

Moderation Policy

These are the people that are listening and responding to your questions.

The Project Team

Public Works

{{ question.username }} asked

{{question.description}}

{{ answer.respondent.name }}
| Edited

Answer this question

Select the respondent who will be marked as answering the question

Provide the answer to the question. Answer can be saved as draft and published when complete.

No questions found